Monitoring plan

Monitoring Plans for this methodology shall include at a minimum, but are not limited to, tracking of the following information:

  • amount of biomethane injected into the grid

  • mass and waste status of each feedstock input in tonnes of fresh matter (ensuring the dedicated crop and ILUC risk thresholds are not surpassed, see Environmental and Social Do No Harm and Leakage)

  • repartition of solid, liquid and raw digestate

  • amount and type of electricity use on-site

  • description of any major changes in operations

The Project Developer is the party responsible for adhering to the Monitoring Plan.